April 2000 to September 2000

Title & Description of AssignmentType of AgreementDate of Inviting
Expression
of Interest
Expected DurationName and Tel. No. of Contact Person

Infrastructure for Penny's Bay Development - Landscape Design

D

Apr 2000

34 months

Mr P. D. MORGAN
2762 5511

10-year Extended Landslip Preventive Measures Project, Phase 2, Package D -Investigation, Design and Supervision of Landslip Preventive Works on Government Slopes and Related Studies

DC

Apr 2000

48 months

Mr K Y CHOI
2760 5773

10-year Extended Landslip Preventive Measures Project, Phase 2, Package E -Stability Studies of Private Slopes

I

Apr 2000

24 months

Mr K Y CHOI
2760 5773

Environmental Monitoring and Audit for Penny's Bay Reclamation, Stage 1

I

May 2000

16 months

Mr K. K. CHAN
2762 5604

Environmental Impact Assessment for Yung Shue Wan Development, Engineering Works, Phase 2

I

Jul 2000

12 months

Mr W. C. LUK
2762 5521

10-year Extended Landslip Preventive Measures Project, Phase 2, Package F -Investigation, Design and Supervision of Landslip Preventive Works on Government Slopes and Related Studies

DC

Jul 2000

48 months

Mr K Y CHOI
2760 5773

10-year Extended Landslip Preventive Measures Project, Phase 2, Package G -Investigation, Design and Supervision of Landslip Preventive Works on Government Slopes and Related Studies

DC

Jul 2000

48 months

Mr K Y CHOI
2760 5773

Water and Sewerage Works on North Lantau for Penny's Bay Development -Design and Construction

DC

Sep 2000

36 months

Mr P. D. MORGAN
2762 5511