Tenders invited for road and tunnel works of Liantang/Heung Yuen Wai Boundary Control Point project

The Civil Engineering and Development Department (CEDD) today (November 16) invited tenders for the contract for the road and tunnel works of the Liantang/Heung Yuen Wai Boundary Control Point.

The works mainly comprise:
* construction of a dual two-lane trunk road including an approximately 4.8-kilometre vehicular tunnel linking up the proposed Sha Tau Kok Road interchange and the Fanling Highway interchange;
* construction of an administration building and three ventilation buildings; and
* tunnel electrical and mechanical works and associated works.

The works are scheduled to commence in May 2013 for completion in November 2017.

The CEDD has commissioned AECOM Asia Company Limited to design and supervise the works. Interested contractors may obtain the tender forms and other particulars from AECOM at 8/F, Tower 2, Grand Central Plaza, 138 Sha Tin Rural Committee Road, Sha Tin.

The invitation to tender was gazetted today. The closing time for the tender is noon on January 25, 2013. Tender submissions should be placed in the Government Secretariat Tender Box at G/F, East Wing, Central Government Offices, 2 Tim Mei Avenue, Tamar.

For enquiries, please call AECOM at 3922 9338.

Ends/Friday, November 16, 2012
Issued at HKT 11:00

NNNN